|

 Home > Business Partnerships > Resources for Business Partners > Use of Hydraulic Concrete Crusher in Demolition Works
 |
| Use of Hydraulic Concrete Crusher in Demolition Works |
|
 |
|
This guideline is to share the information with the Construction Industry on the use of Hydraulic Concrete Crusher (HCC) for demolition works and on the implications of its use based on the experience gained in the trial use of HCC in a number of Housing Authority (HA) projects.
|
 |
|
In an attempt to address the problems of frequent public complaints about excessive noise nuisances from HA demolition sites, the HA initiated studies, with advice kindly given from the Environmental Protection Department (EPD), to find out ways to minimize these nuisances to nearby Noise Sensitive Receivers (NSRs). The use of HCC was recommended for further investigation and trials had been conducted in some selected projects. The findings from these trials gave very encouraging results in noise reduction during demolition processes. This guideline summarizes experience gained and results obtained from these trials with a view to providing project teams with useful information on the use of HCC in demolition projects.
|
 |
|
Statutory Requirements on Noise Control
Although currently there is no statutory requirement on the permissible maximum noise level emitted from a demolition site, the HA specification does impose a maximum noise limit according to an EPD's advisory document, Practice Notes to Professional Persons (ProPECC) PN 2/93, issued in May 1993. The maximum noise levels specified in the HA's Standard Specifications were developed based on this ProPECC. (Appendix 1)
Currently, the most popular mechanical plant used in demolition works is the excavator mounted Hydraulic Breaker (HB). Since the operation principle of HB is by percussive striking actions of its chisels, the sound power level for HB can be as high as about 122 . If the noise level reduction is purely relied on distance attenuation, it may require about 84 to 93 metres in order to reduce to a level of 75 . For two HBs working at the same time, the distance required may be up to 120 to 130 metres.
|
|
General
To reduce the noise nuisance during the demolition works, the following methods can be considered:
|
1. |
Use of quieter plants and equipments; |
|
|
|
|
2. |
Use of noise barrier between the noise source and NSRs; |
|
|
|
|
3. |
Use of acoustic enclosures; and |
|
|
|
|
4. |
Other methods. |
|
|
|
|
|
Use of Quieter Plants and Equipments
There are various quieter plants, equipments or methods available for demolition works, such as HCC, saw-cutting, chain-cutting, high-pressure water jet and expansive chemicals. However, apart from HCC, the others are only practical in small-scale demolition works.
|
Use of Noise Barrier between the Noise Source and NSRs
The principle of noise barrier is to stop airborne noise by placing a barrier at the transmission path between the noise source and the NSR. The noise barrier is made with dense material, with high noise damping factors and with sound absorptive materials at the noise source to minimize reflection, which includes:
|
1. |
Special made movable noise barrier
Noise barrier can be a special made moveable / demountable type and can be moved around during the demolition. However, it is more difficult in supervision to ensure the contractor using the barrier correctly. In addition, there are problems to be overcome on site like demolition at edges of the building. |
|
|
|
|
2. |
Use of existing buildings as noise barrier
Existing buildings are very effective in acting as noise barriers. By scheduling the demolition sequence properly, existing buildings can be made use as a noise barrier to minimize the noise impact to nearby NSRs. An example of a very successful contract was to make use of a residential block as the noise barrier between the site and a school. The block was then demolished at the very last time when the school was at summer vacation. |
|
|
|
|
3. |
Other methods
Use of noise-damping sheets hung at the scaffolding can be considered in some cases. However, this depends on factors like cost of noise-damping sheets, stronger scaffolding required and the location of the NSR. |
|
|
|
|
|
Use of Acoustic Enclosures
Noises from a demolition process are mainly airborne and structural borne. It is rather difficult to minimize the structural borne noise (from the vibration of the machinery and the building elements). The airborne noise is comparatively easier to handle. Using acoustic enclosure is one of the ways, which includes:
|
1. |
Enclosure for the HB
The most common method is using an enclosure for the HB. At present, some HBs in the market claim to be designed to lower sound power levels (10 ) than ordinary HBs and / or made with materials with higher noise damping factors such as "Incramute". Some of them are with built-in acoustic enclosures, such as the brands "Krupp" and "Rammer". There are also excavators with lower noise level than ordinary ones and with a reasonable cost. The other method is by fixing noise-damping sheets onto the booms of the excavator. However, it is not very cost effective. |
|
|
|
|
2. |
Enclosure for the plant / working area
This method is being adopted in some other countries to enclose the whole working area by acoustic enclosures. The method is very expensive and given the site constraints commonly encountered in Hong Kong, it is considered not practical. |
|
|
|
|
|
Other Methods
There are other various noise reduction methods, but they are also impractical for the use at construction sites. One example of these methods is the "active" method by using out-phased noises to counter-reduce the noise emitted and combinations of different demolition methods to be used together. Another example is the saw-cutting method to cut the building into larger pieces and transport them to ground level by crane. HCC or crusher will then be used to break them into smaller sizes.
|
 |
|
The use of HCC is at present the most practical and economical demolition method, with its low noise emission and effectiveness having been verified in previous trials. This method provides a practical solution if the predicted noise level at nearby NSRs will be exceeded by using traditional HB.
What is HCC?
Both HB and HCC are excavator mounted mechanical tools for demolition works. The action of HCC is by the opening and closing of its jaws to crush concrete, powered by the hydraulic fluid supplied by the excavator. For details, please refer to Appendix 2. The main noise source from HCC is from the excavator itself. Noises created by HCC and its crushing actions are very low and can be negligible in noise assessment. Currently, the supply of HCC in Hong Kong is limited and requires a delivery time of about one month. HCC is commonly used in other countries and there are wide ranges of types and suppliers of HCC from most construction plant manufacturers (Appendix 2).
|
 |
The Trial Projects
A small-scale trial was carried out in mid-February 2001 in the demolition project at Valley Road. In this trial, four levels of a seven-storey block were demolished by using HCC. In the same year, the use of HCC was specified in a Ho Man Tin redevelopment project for blocks next to a school. In early 2003, the mandatory use of HCC was specified in a demolition project in Lam Tin. All these projects were very successful in noise reduction and owners of all NSRs were satisfied with the noise levels even when demolition works were as close as at within 10 metres at some locations.
|
|
Safety Precautionary Measures
These trial projects only involved demolition of seven-storey high residential blocks and therefore structural member sizes were less than 450 millimetres in width / thickness. HCCs used were not heavy duty and the weight of excavator used could be as low as 12 tonnes. However, if a larger size HCC is required for thicker member sizes, the excavator mounted has to be much heavier. This is because the excavator has to provide sufficient hydraulic fluid for the operation of HCC and to act as a counter-weight for HCC. It is therefore necessary to select the suitable HCCs for the demolition works at the planning stage by considering:
|
1. |
Maximum structural member sizes; |
|
|
|
|
2. |
Maximum jaw opening width of HCC; and |
|
|
|
|
3. |
The capacity of excavator to be mounted. |
|
|
|
These should be carefully considered in the design of temporary supports for the demolition works.
In addition, in the crushing process of HCC, it could be rather difficult to control the falling of small-sized debris from the parametrical walls and beams. The following safety precautionary measures are recommended if HCC is to be used:
|
1. |
The scaffolding to be double layer type bamboo or steel scaffolding; |
|
|
|
|
2. |
The protective screen to be thicker and stronger; |
|
|
|
|
3. |
More frequent cleansing of debris at catch-fans is to be carried out to prevent over-loading of the catch-fan. Cleansing on daily basis is recommended; |
|
|
|
|
4. |
Adequate supporting props and false-works have to be provided, the design of which must be prepared and certified by qualified engineer; and |
|
|
|
|
5. |
The HCC operator should be trained by demolishing minor structures at ground level and with sufficient experience. |
|
|
|
|
|
Cost and Time
|
1. |
Cost
There was no significant cost increase in these trials probably because all buildings were low rise and with limited scope of works. For future projects, however, project teams are advised to consider the following costs when using HCC, assuming it is to demolish five blocks and the project sum is HK$10,000,000, with 30% preliminary cost:
|
|
|
(a) |
Plant cost
The cost to buy a HCC is about HK$300,000, excluding the excavator (HB is about HK$200,000). The contractor may rent the whole set of plant at about HK$7,000-8,000 per day (HCC + excavator).
The additional plant cost is within HK$100,000, which is about 1% of the contract sum.
|
|
|
(b) |
Overhead Cost
Since the use of HCC requires longer contract periods, therefore, an increase in the contract sum to cover the higher overhead cost is expected. Table 3 gives an estimation on the increase basing on the extended contract period.
Table 3: Estimation on the Increases in Overhead Cost of Using HCC
| No. of Storeys |
App. Original Programme (Months) |
Extended to |
Time Increased (%) |
Preliminary Cost Increased |
| 7 |
7 |
7.57 |
8.1 |
1.62 |
| 12 |
8 |
8.97 |
12.2 |
2.44 |
| 16 |
8.5 |
9.8 |
16.5 |
3.3 |
|
|
|
|
Assuming the preliminary cost is 30% and linearly distributed (In general, the preliminary cost is around 20% and with more heavy weightings at the beginning of the contract) |
|
|
|
|
|
|
(c) |
Operational Cost
The other operational costs provide for more frequent cleansing of catch-fan and stronger safety screen. The increase in cost is around HK$100,000, which is about 1% of the contract sum. |
|
|
|
|
2. |
Time
In the trial projects using HCC, although standard contract period was adopted without any extension, contracts were completed on time. This might probably be due to the fact that these projects only consisted of seven-storeys blocks and additional time required by HCC (14 days) could be absorbed within the normal contract period specified. However, it is recommended to lengthen the contract period in case the use of HCC becomes mandatory. The extra time required may be estimated basing on Table 2. |
|
|
|
|
 |
|
Although the use of HCC can solve most of the problems in noise nuisance created during demolition works, it is necessary to consider the following before specifying the use of HCC in demolition contracts.
|
|
Time and Cost
|
1. |
Time
Since HCC is slower than HB and requires longer demolition period, it is necessary to ensure that this can be tolerated in the overall project programme. Reference can be made to Table 2 for estimation of extra time required. |
|
|
|
|
2. |
Cost
Referring to Section 6, the use of HCC may increase the contract sum by around 5%. It is necessary to ensure that the project budget is sufficient to cover this. Reference can be made to the above section of The HCC Trials - Cost and Time for estimation. |
|
|
|
|
|
Need
Since the use of HCC will increase both the contract sum and the contract time, before deciding to use HCC, it is worthwhile to consider the following:
|
1. |
Will the noise level exceed the specification? (Carry out a noise level estimation on the closest NSR using the method specified in the TM (Appendix 1), assuming HB has SPL = 122 ). In case the blocks are with considerable floor area, more than one HB may be used. |
|
|
|
|
2. |
In case the predicted noise level exceeds the allowable limits, can quieter type HB (those with acoustic enclosures) be used instead of HCC? |
|
|
|
|
3. |
Apart from HCC, are there any other feasible methods that can be used to reduce the noise impact? For example, can demolition works be carried out on school holidays? Or can the demolition sequence be planned to make use of existing blocks as noise barriers, etc.? |
|
|
|
|
4. |
Can the project allow the additional time and cost for using HCC? |
|
|
|
|
5. |
Will there be any other benefits and considerations in using HCC, for example, reduced vibration and improved public images, etc.? |
|
|
|
|
 |
Observations and experiences gained in the trials mentioned in this report suggested that HCC is one of the effective and practical tools to minimize noise nuisance. It is especially useful for demolition works with NSRs within 100 metres around the site where the use of HB will most likely exceed the allowable noise limits. However, due to the extra time and costs required, the project team should carry out an assessment on noise impacts to nearby NSRs at the planning stage, and consider other feasible methods at the same time in order to arrive at the most cost effective and practical solution to suit their own site constraints and concerns.
|
| |
|
 |
|
Appendix 1: Regulatory Ordinance, Regulations and Practice Notes
|
1. |
Noise Control Ordinance (Chapter 400), Laws of Hong Kong; |
|
|
|
|
2. |
Factory and Industrial Undertakings (Noise at Work) Regulation, under Section 7 of the Factories and Industrial Undertakings Ordinance (Chapter 59), Laws of Hong Kong; |
|
|
|
|
3. |
Practice Notes for Professional Persons (ProPECC) PN 2/93 - Noise from Construction Activities - Non-Statutory Controls, May 1993; and |
|
|
|
|
4. |
Technical Memorandum on Noise from Construction Works Other than Percussive Piling, re-print, February 1998. |
|
|
|
|
|
Appendix 2: Common Types of HCC
There is a wide range of suppliers of different types of HCC. In the selection of the suitable HCC, it is necessary to consider:
|
1. |
The minimum weight of the carrier excavator; |
|
|
|
|
2. |
The maximum jaw opening size (maximum member size < 0.7x maximum jaw opening is recommended); and |
|
|
|
|
3. |
HCC with the 360 rotation function. |
|
|
|
Basing on the requirement of weight of the plant at working level to be less than 11 600 kilograms (HA Standard Specification Clause DEM 1. W380.2), the following are some feasible examples. (For heavier plants, relevant approvals are necessary.)
| Brand |
Mantovani
Benne |
Brokk |
NPK |
Sango |
Atlas Copco |
| Model |
CR5 |
CC 620 |
S-15X |
TS500RCD |
HCC 550 |
| Made |
Italy |
Sweden |
Japan |
Japan |
Sweden |
| Carrier Weight (ton) |
5 - 14 |
4 |
10 - 18 |
6 - 11 |
5 - 14 |
| Weight (kg) |
520 |
480 |
1410 |
550 |
570 |
| Output (ton) |
50 |
45 |
70 |
40 |
- |
| Working Pressure (bar) |
200 - 250 |
250 |
210 |
210 |
150 - 250 |
| Oil Flow (l/min) |
50 - 90 |
60 - 120 |
80 - 150 |
- |
50 - 90 |
| Max. Opening Width (mm) |
450 |
620 |
750 |
500 |
450 |
360 Rotation |
Yes |
Yes |
Yes |
Yes |
Yes |
|
Last revision date: 2 July 2004
|