52 targets were made for the year 2006/07 ranging from awareness and participation, water conservation, greening and landscape, control of hazardous materials, noise nuisance, waste management, energy efficiency, safety performance, economic, and social. Of these targets, 49 were fully met, 2 achieved substantial progress and 1 fell short.
2005/06 Target Performance

Action Plan for Targets Not Fully Met
|
|
|
Targets |
Progress |
Action Plan for 2007/08 |
Further abate the remaining asbestos containing materials in existing HA managed properties by implementing asbestos abatement programme through estate redevelopment programme and asbestos removal works |
Up to March 2007, five blocks of Cheung Sha Wan Flatted Factory (FF) were demolished and asbestos containing materials in four blocks of San Po Kong Flatted Factory were removed, which resulted in 1.7% asbestos removal. However, when calculating asbestos abatement in terms of removal from a number of blocks, we only achieved 0.9% asbestos removal. |
To continue monitoring the progress and take action if necessary. |
|
|
|
Reduce domestic waste to
0.7326 kg per person per day. |
Up to March 2007, 99.6% of the target was achieved. |
To continue monitoring the progress and take action if necessary. |
|
|
|
Issuance of consolidated safety manual and design checklist. |
Site safety handbook and guidelines are under preparation. |
To continue monitoring the progress and take action as necessary. |
|
|
|

|