In the past year, we have removed a further 3% of the
known asbestos from our estates. Since we started our Asbestos Abatement
Programme in 1989, we have removed 90.7% and set targets to remove
the rest. All asbestos removal is carried out in accordance with the
requirements of the Air Pollution Control Ordinance. For buildings
where asbestos remains, we continue to closely monitor their condition
until they are abated.
Under Phase 3 of our joint asbestos investigation and management programme
with EPD, we surveyed a further 126 schools in public housing estates
and are now reviewing the results. To date, we have surveyed 245 schools.
There is no imminent risk of asbestos fibre release in schools. Nevertheless,
we have taken action to monitor and abate asbestos containing materials.
|
 |
After discussions with EPD, we arranged trials on collecting
and disposing of spent fluorescent lighting tubes and other mercury
containing lamps at 2 estates and demolition sites. This is so we
can prepare for when regulations come into force requiring mercury-containing
lamps to be disposed of safely in accordance with the Waste Disposal
(Chemical Waste) (General) Regulation.
|
 |
|